METHOD STATEMENT
FOR
uninterruptible power supply installation
Ø TABLE OF CONTENTS
1. SCOPE
2. definitions
3. HEALTH AND SAFETY
4. OPERATION
5. installation and fixation
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTs REQUIREMENTs
10. WASTE MANAGEMENT
11. SPECIAL CONTROL MEASURES.
12. SUPPORTING DOCUMENTATION
13. DISTRIBUTION
1.SCOPE
Ø This procedure to clear the method of the supply, installations of Uninterruptible Power Supply for the project.
Ø This document details Uninterruptible Power Supply Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. definitions
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH AND SAFETY
Ø Strictly followed as per the manufacturer's Health and Safety recommendations for handling and use of the materials.
Ø Ensure all involved personnel shall be aware of the same.
Ø Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.
4. OPERATION
Ø Material:
· Material used will be as approved by the Engineer.
· The sizes and routes routing will be as per the approved Shop Drawings.
Ø Storage and Protection:
· Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
· Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
5. INSTALLATION and fixation
Ø Pre-Installation:
· The delivery vehicle will be parked in the loading area; the equipment will be unpacked removed from vehicle using the tail lift.
· Verify compliance between type label on reverse side and system ordered.
· Check input and output voltage.
· Copy the type label data to label copy below for easy identification of the system.
· Use a fork lift or pallet to transport the system to installation site.
· Open UPS doors and unscrew metal straps mounted on front cover of UPS.
· The UPS equipment will then be moved into position using scoots and pallet trucks.
· The batteries and stand will be moved into the UPS room using pallet trucks.
Ø Installation for UPS:
· All parts are accessible from front or top of UPS.
· Identify and check against delivery note all batteries, links and cables are sufficient and correct.
· Study the installation guide and layout drawings supplied by the manufacture.
· Attach incoming and out-going cables to terminals.
· Always keep AC, DC and communication able separate.
· Follow the installation guide for power and communication cable entry.
· Use commercially available approved solderless lugs for the wire size required for your application. Connect wire to the lug using appropriate tool.
· Input, output and DC cables are routed in separate conduits.
· Verify all power connections are tight.
· Verify all control wire connections are tight.
· Verify all power wires connections have proper spacing between exposed surfaces, phase to phase and phase to ground.
· Verify that all power & control wires are run in individual, separate conduits.
Ø Installation for Battery:
· Load new batteries paying particular attention to placement according to diagram and polarity.
· Connect positive and negative feeds to the start and finish of the string
· Connect one of the centre links and note the voltage and polarity.
· The installation of batteries requires battery knowledge and should only be carried out/supervised by qualified electricians familiar with batteries. Keep unauthorized personnel away from batteries.
· Avoid rough treatment and opening of batteries. Released electrolyte is harmful to skin and eyes, and may be toxic.
· During installation, remove watches, rings, and other metal objects.
· Use tool with insulated handles.
· Wear rubber gloves and boots.
· Do not leave tools or metal parts on top of batteries.
· Disconnect charging source prior to connecting batteries.
· Determine if the battery is inadvertently grounded. If inadvertently grounded, remove unwanted ground source. Any contact with grounded batteries may result in electric shocks. The likelihood of shocks will be reduced if grounds are removed during installation and maintenance.
· After installation of UPS, Engineer-in-charge shall check the complete works and complete the Inspection checklist for UPS installation works.
· Engineer-in-charge shall arrange and request for inspection with the Owner’s representative M&E Residential Technical Officer (RTO) using approved Main con Request for Inspection (RIN) form.
Ø Commissioning:
· Check the power quality of UPS output.
· Check whether the harmonics are within the limit
· Check the transfer time.
· Check the sine wave composition.
· Check battery voltage and internal resistance of each cell, including inter-cell and inter-tier connectors.
· Check the temperature of battery.
· Check the currents and discharge events.
· Check the individual cell voltage.
· Check to verify that the UPS systems are performing to manufacturer specifications.
Ø Technical Assistance:
· The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.
· This instruction shall be scheduled at the convenience of the staff.
· All such instruction shall be properly recorded.
· WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shop drawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
Ø PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.
2. To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.
3. To ensure that all the equipment and material required executing the work are available according to the planned construction program.
4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
Ø SITE ENGINEER
1. To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.
2. To provide all necessary information and distribute responsibilities to his construction.
3. To monitor the progress of work in relation with the work program and to report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.
Ø FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.
3. To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.
4. To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.
5. To control disposal of waste materials according to the instructions received from the site engineer.
6. To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.
7. To inform the site engineer regarding areas ready for inspection.
8. Foreman and the storekeeper are responsible for the distribution and control of materials.
Ø SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe working on the site.
3. Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.
4. Ensure that the site is maintained clean and tidy.
Ø TECHNICIAN FROM SUPPILER
1. The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.
2. Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
3. Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
4. Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
Ø STORE KEEPER
1. Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
2. One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
· Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
· Uninterruptible Power Supply Components and Accessories
9. EQUIPMENTs REQUIREMENTs
· The Equipment that will be engaged for Uninterruptible Power Supply Installation will be as follows:
1. Hand Tools
- Power Tools (if required)
- Electrical Drill (only for surface installation works)
- Diagonal-Cutting Pliers
- Wire Stripper/Cutter with Spring
- Side-Cutting Pliers
- Shank Screwdriver/Flat screw driver
- Compression lug crimp tool
- Cable to service bypass panel from system feeder
- Cable to UPS input from service bypass panel
- Cable to UPS input from external batteries
- Necessary conduit for above listed cabling
- Knock out set (for conduit)
- P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves & safety vest )
10. WASTE MANAGEMENT
Ø The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
11. SPECIAL CONTROL MEASURES
Ø The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :
· Proper PPE must be worn at all time
· Permit to work at height > 2m where applicable
· Lifting operation permit (using crane) where applicable.
· Confined space permit where applicable.
· Approved work method statement and risk assessment will be made available to site.
· All workers doing the work shall be briefed on this method statement and risk assessment.
12. SUPPORTING DOCUMENTATION
Ø This method Statement should be read in conjunction with the below referenced documentations:
- ITP for Anti – termite Treatment.
- Insulation Resistance and continuity Test Report.
13. DISTRIBUTION
Ø Copy of this method statement shall be issued to the following for information / action / comments:
- Project Manager
- Site Engineer
- Foremen
- Safety Engineer
- Technician From Supplier
- Store Keeper
