TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
3. HEALTH AND SAFETY
4. OPERATION
5. INSTALLATION AND FIXATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
10. WASTE MANAGEMENT
11. SPECIAL CONTROL MEASURES.
12. SUPPORTING DOCUMENTATION
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations of Transformer for the project.
This document details Transformer Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH AND SAFETY
Strictly followed as per the manufacturer's Health and Safety recommendations for handling and use of the materials.
Ensure all involved personnel shall be aware of the same.
Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.
4. OPERATION
Material:
• Material used will be as approved by the Engineer.
• The sizes and routes routing will be as per the approved Shop Drawings.
Storage and Protection:
• Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
• Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
5. INSTALLATION AND FIXATION
Off-Loading:
• Use Fork Lifts or Mobile Crane to off-load the transformers.
• Make sure that the capacity of the fork lifts or mobile crane can carry the weight of the transformers.
• Off load the transformer on the designated off loading area.
• Proper care must be observed during off loading to prevent unnecessary damage or dents on the transformers.
• Ensure that the transformers are properly protected and covered with tarpaulin.
Pre-Installation:
• All materials and documentation relevant to this particular section of works shall be checked by the Construction Department prior to the commencement of works ensuring that these are correct and approved type.
• Before any permanent works will continue, pre-inspection on all materials, tools and access for installation to be carried out.
Installation:
• Before the transformer will be delivered to site, ensure that the transformer railing is fixed as per approved drawings and comply on municipality requirement.
• Move the transformers from the designated off-loading area or storage area using fork lift and set them in position near to the transformer room.
• Make sure that the orientation of the transformer with regards to the position of cable entries is correct.
• Push in the transformers inside the transformer room. Set the transformer on their final positions and make sure that they are properly secured and protected.
• Raise Request for Inspection for Transformer Installation.
• Conduct on site test for the transformer.
• Test shall include winding insulation resistance test and shall conform to manufacturer’s recommendation and specification.
• All tests must be recorded and conducted in the presence of Consultant by manufacturer testing engineer.
• Dress and terminate the incoming and outgoing cables on the transformers.
• Ensure that the cables were supported properly.
• Cable glands, lugs and termination kits shall be approved type.
• After termination works has been completed, clean the transformer cable box and ensure that it is free from foreign materials and excess openings must be sealed off and ensure that all the connections are properly tight and torque.
• Raise Request for Inspection for the cable terminations and dressing.
Commissioning:
• Cover the cable boxes.
• Bolts and nuts must be tightened properly.
• Make sure that the transformer room is clean and free from foreign materials.
Technical Assistance:
• The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.
• This instruction shall be scheduled at the convenience of the staff.
• All such instruction shall be properly recorded.
• WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.
2. To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.
3. To ensure that all the equipment and material required executing the work are available according to the planned construction program.
4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
SITE ENGINEER
1. To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.
2. To provide all necessary information and distribute responsibilities to his construction.
3. To monitor the progress of work in relation with the work program and to report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.
3. To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.
4. To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.
5. To control disposal of waste materials according to the instructions received from the site engineer.
6. To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.
7. To inform the site engineer regarding areas ready for inspection.
8. Foreman and the storekeeper are responsible for the distribution and control of materials.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe working on the site.
3. Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.
4. Ensure that the site is maintained clean and tidy.
TECHNICIAN FROM SUPPILER
1. The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.
2. Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
3. Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
4. Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
STORE KEEPER
1. Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
2. One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
• Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
• Transformer Components and Accessories
9. EQUIPMENTS REQUIREMENTS
• The Equipment that will be engaged for Transformer Installation will be as follows:
1. Hand Tools
2. Power Tools (if required)
3. Diagonal-Cutting Pliers
4. Wire Stripper/Cutter with Spring
5. Side-Cutting Pliers
6. Shank Screwdriver/Flat screw driver
7. Compression lug crimp tool
8. Necessary conduit for System Cabling
9. Knock out set (for conduit)
10. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves & safety vest )
10. WASTE MANAGEMENT
The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
11. SPECIAL CONTROL MEASURES
The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :
• Proper PPE must be worn at all time
• Permit to work at height > 2m where applicable
• Lifting operation permit (using crane) where applicable.
• Confined space permit where applicable.
• Approved work method statement and risk assessment will be made available to site.
• All workers doing the work shall be briefed on this method statement and risk assessment.
12. SUPPORTING DOCUMENTATION
This method Statement should be read in conjunction with the below referenced documentations:
ITP for Anti – termite Treatment.
Insulation Resistance and continuity Test Report.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
5. Technician From Supplier
6. Store Keeper

👆👆👆👆
ReplyDelete